DOE Solar-Thermal Demonstration

NELHA

Kailua-Kona, Hawaii

At NELHA's HOST Park, the U.S. Department of Energy and NELHA funded a nominal 500 m³/day forward-osmosis plant running on process heat from an existing 2 MW solar-thermal array and thermal storage. Trevi engineered and integrated the plant; NELHA supplied the site and seawater infrastructure.

The project

Funding, Construction, and Operation

In 2018, DOE and NELHA defined a next-generation forward-osmosis system sized to a nominal 500 m³/day, paired with NELHA's existing 2 MW solar-thermal array and hot-water thermal storage at HOST Park in Kailua-Kona. Trevi was the main technology contractor and integrator.

The plant was built and operated from June 2022 to September 2023, documented in the DOE-hosted final report.

Award
DE-EE0008403 · $1,928,238 DOE award · $2,311,938 awardee cost share (DOE project listing)
Site
NELHA HOST Park, Kailua-Kona, Hawaii · Existing seawater intakes and a 2 MW solar-thermal array
Nominal design
500 m³/day forward-osmosis system, proposed by DOE and NELHA
Report period
Operated June 2022 – September 2023 (DOE-hosted final report)

500 m³/day describes the project's design basis.

Trevi forward-osmosis plant at NELHA, Keahole Point, Hawaii
NELHA-supplied seawater infrastructure and Trevi's forward-osmosis plant, integrated at HOST Park in Kailua-Kona.
What was integrated

Four Connected Systems

The project tied Trevi's forward-osmosis plant into infrastructure NELHA already operated at HOST Park: feed seawater, membrane transfer, process heat, and final water handling in a single demonstration.

  1. 01

    Seawater supply

    NELHA's HOST Park intakes supplied feed seawater to the plant.

  2. 02

    Forward-osmosis transfer and draw recovery

    A membrane loop moved water across an osmotic draw; a separate stage recovered and regenerated the draw solution.

  3. 03

    Solar-thermal heat and storage

    NELHA's 2 MW concentrating solar-thermal array and hot-water thermal storage supplied process heat; a natural-gas-fired boiler in the plant's energy boundary at times ran alongside the solar system.

  4. 04

    Final water handling and measurement

    Permeate passed through final handling before sampling; the final report records handheld salinity measurements from operating runs.

Explore Forward Osmosis
Project sequence

From Award to Operating Plant

From funding through commissioning to documented results.

  1. 01

    Fund and define

    DOE award DE-EE0008403 provided $1,928,238, with $2,311,938 in awardee cost share, for a nominal 500 m³/day forward-osmosis design paired with NELHA's 2 MW solar-thermal array.

  2. 02

    Design and fabricate

    Trevi engineered the membrane trains, draw recovery, heat exchange, and controls around NELHA's site infrastructure and thermal source.

  3. 03

    Install and integrate

    The plant was installed at HOST Park and connected to NELHA's seawater intakes, solar-thermal array, and thermal storage.

  4. 04

    Commission and operate

    The plant operated from June 2022 to September 2023, producing permeate (DOE-hosted final report).

  5. 05

    Measure and learn

    Recovery rates at times exceeded 65%. The final report also documents a commissioning milestone that was not met, carried forward as project learning.

Published sources

Published Sources

The Toyobo account and the DOE-hosted final report are reported separately.

Attributed and reported accounts

One project, two performance accounts

AttributedToyobo MC · February 2024
Reports completion, 500 m³/day production, and recovery above 65%
Toyobo MC
PublishedDOE-hosted final report
Permeate produced during daily operating runs, June 2022–September 2023
DOE / NELHA final report
MeasuredWater quality versus rate
Less than 500 ppm TDS at low rates; 500–700 ppm at higher rates as extractor imbalance limited acceptable output
DOE / NELHA final report
Published100-hour go/no-go target
Required >20 m³/hour steady state; the report states it was not achieved
DOE / NELHA final report
AttributedDaily production window
Trevi's own account: a solar-thermal storage limitation held production to 4–6 hours per day
Trevi project account